So as of 1:00 pm this afternoon this is where are in the construction of our house:
- siding is all on the house, still needs to be painted
- windows installed
- fireplace installed
- electricity ran and inspected
- plumbing ran and inspected
- gas lines ran and inspected
- roofing delivered, tar paper in place
- insulation installed in walls
- furnace in place
- drywall delivered
Things we are looking forward to happening this week hopefully:
- roof put on
- house painted
- masonry on front of the house possibly started
- drywall put up
- texturing walls
I'm sure there are a million other little things going on that we aren't aware of, but it's totally taking shape. When you pull up to it now, you can see what its going to look like!! I'll post some pictures here soon, I just need to gather them from Louis' phone and my phone so I can make an out of order post for you guys! :)